The NHS will end its current contract with Palantir in March 2029 while launching a new procurement programme intended to increase competition, reduce dependence on individual technology suppliers, and improve interoperability across health services.
Health minister James Frith confirmed the decision in Parliament on 16 November, outlining plans for the next generation of the NHS Federated Data Platform (FDP).
The existing platform is supplied by a consortium led by Palantir Technologies, which secured the contract in November 2023. The agreement began in March 2024 and includes provisions allowing its duration to be extended.
Ministers have decided to maintain the current arrangements for approximately two further years rather than exercise the earliest contractual break option in 2027. Funding will continue at the existing annual rate during the extension.
Market engagement for the replacement programme will begin in January 2027, with formal procurement scheduled for the second half of that year. The government expects the full process, from engagement to completion, to take approximately 18 months.
The competition will be open to UK and international suppliers, including smaller technology businesses and companies developing specialist AI capabilities.
Frith said the NHS intends to create more opportunities for British suppliers while reducing reliance on proprietary systems that are difficult to replace or integrate with other technologies.
The decision ends the existing contractual arrangement in 2029, but does not prevent Palantir from competing for future work. Ministers have committed to an open procurement process rather than announcing the exclusion of an individual supplier.
Procurement and operational continuity —
The FDP connects information held across NHS organisations to support operational activities including waiting-list management, theatre scheduling, patient discharge, and the coordination of hospital resources.
The existing contract was originally valued at up to £330m over its potential full duration. That figure represents a contractual ceiling rather than expenditure already incurred.
According to figures presented by the minister, 170 NHS trusts have signed up to the platform and 142 have activated it. The government maintains that 137 are realising operational benefits.
Those figures were challenged during the parliamentary debate. MPs raised concerns that activation did not necessarily establish meaningful usage and questioned whether previously reported benefits accurately reflected activity across individual trusts.
Frith acknowledged the distinction between signing up, activating a system, and demonstrating operational value, and said that overstated performance claims should be corrected.
The government intends to continue operating and expanding appropriate uses of the existing platform during the transition. NHS organisations have been encouraged to use its current capabilities while the replacement arrangements are developed.
Changing suppliers will require attention to the ownership and transfer of technology, including the intellectual property and contractual rights associated with the current service.
Frith told MPs that the existing agreement includes exit and transition provisions, that migration is possible in principle, and that intellectual property funded by the NHS is distinct from the supplier’s pre-existing intellectual property.
The next platform is expected to place greater emphasis on common data standards and interoperability, enabling systems developed by different providers to exchange information more consistently.
Cybersecurity and patient information controls will also form part of the new approach, with ministers planning to involve frontline NHS staff, patients, the National Data Guardian, and a dedicated patient panel in developing the requirements.
Additional capabilities may include systems supporting maternity services, although the detailed specification has not yet been determined.
These decisions will influence the structure of the procurement and the extent to which individual suppliers can provide components or services without controlling the wider technology environment.
The government expects the current FDP to remain operational during the procurement and transition period, with the replacement arrangements intended to take effect when the existing contract ends in March 2029.